A construction progress update in provided for your viewing below. Please let me know if you have any questions or concerns.
Thank you
Joan
Construction on north half of the road :
· Installation of band curbs at corner features
Construction on south half of the road:
· Installation of street light poles to follow sidewalk completion
· Installation of band curbs at corner features
· Water main tie-ins
· Installation of signal pole foundations at “D” and “A”
· Installation of conduits for franchise utilities
Also continual:
Redesign of handicapped ramp at “B” and 10th and discussions with property owner
Discussions with FDOT regarding requirements for pavers vs. concrete at 10th and Dixie – information from FDOT expected late May
Discussions with the County for a change in timing/ light fixture at the intersection of “A” and 10th