Wednesday, September 26, 2012

Roadway Restoration - South Ocean Boulevard

PALM BEACH, Florida – The Town has begun the roadway restoration portion of the A-39 to A-7 Force Main Replacement project.  The work will be divided into three work areas:
    o South Ocean Boulevard between Phipps Ocean Park and Southern Boulevard began September 25, 2012, and is anticipated to be completed on October 10, 2012.
    o South Ocean Boulevard from South County Road to El Bravo Way and then on South County Road from El Bravo Way to Island Road.  This work will take place from October 4, 2012 through October 12, 2012.    
    o South Ocean Boulevard from Southern Boulevard to South County Road is scheduled from October 23,2012 to November 2, 2012.
This schedule is tentative and may be impacted by weather.

Traffic will be directed by flaggers.  Please observe the construction signage and safety barricades within the project and use caution when traveling in this area.

The Town’s force main Construction Manager, Burkhardt Construction, will have their contractor, Ranger Construction complete the roadway restoration.  Please contact Wayne King, with Burkhardt Construction with any questions or concerns at 561-718-2605 or email fmain@townofpalmbeach.com.