Wednesday, April 29, 2009

10th Avenue Construction Up-date

Construction on north half of the road (continued from last week):

·         Installation of street light poles

·         Signal pole foundation continues

·         Corner feature installation

 

Construction on  south half of the road (continued from last week):

·         Installation of conduits to the concrete poles in the alleys

·         Installation of concrete curbs

 

Ongoing – installation of concrete curb, asphalt patchwork, utility installation

 

Electric cables are being shipped in 5/1/09

 

Also continual:

Negotiations with Comcast regarding upgrades and costs

Redesign of handicapped ramp at “B” and 10th and discussions with property owner

Discussions with FDOT regarding requirements for pavers vs. concrete at 10th and Dixie